"Why does this tank cost this much?" — a quote shows only the total, but that number builds up bit by bit across 21 steps, from the moment the specs are set to site qualification after installation.
Using one 400 L jacketed pressure vessel as the example, we laid out what cost is added at each step as an animation.
5-minute video — the 21 steps of building a 400 L jacketed tank and the cost added at each one
Scroll down and the tank gets built while the amount on the right builds up.
Plates cut, bent and formed, then welding, inspection and insulation through to installation — the 21 steps as a picture.
See the 21 steps of a quote →
The amount builds up in five streams
Material — set by plate thickness and size and the number of plates ordered. Different thicknesses mean separate plates.
Labor — time for design (size, thickness, drawings, documents, plus the detail design of fittings) and for cutting, polishing, welding and assembly.
Machining · outsourcing — work usually sent out: bending and forming, nozzles and girth flanges on the lathe, base plates on the laser, RT, EP.
Bought-in parts — accessories like valves, gauges, rupture discs, temperature sensors and relief valves. Taken here as roughly 20% of the total, but it differs with every company and spec.
Inspection · permits, transport · installation — pre-weld inspection, the hydrostatic test, and crane and transport. The installation inspection is the customer's, so it is not in the fabricator's quote.
The slow part of a quote is at the very front
The first six steps — setting the size, calculating the internal and external pressure thickness for it, making the drawings and permit documents, and producing the pressure-part order list and cutting plan — have to be calculated and drawn by people.
A jacketed tank in particular is pressed from outside (buckling), so no single formula finishes it: you assume a thickness, read two charts and go thicker again.
AUTONEST VC finishes these first six steps with a single input, and also gives the numbers used later on the shop floor (RT film count, hydrotest pressure, weight). What remains for the designer is the detail and machining drawings of fittings like nozzles, manhole and legs (step 8, detail design).
Amounts on the page are examples to aid understanding; real quotes differ by company, spec and site.
Shorten the first six steps yourself.
Enter the type and capacity and you get the size, thickness, drawings, permit documents, order list and cutting plan.
Explore AUTONEST VC →